Nord Stream chose pipe contractors

Photo: Gazprom.ru

Nord Stream will commission Europipe (Germany), OMK (Russia) and Sumitomo (Japan) with the supply of one million tons of steel pipes for the construction of the second pipeline of the Nord Stream project, the Nord Stream consortium informs.

Location

The contract value is approximately one billion EUR, of which German Europipe will be awarded 65 percent, the Russian pipe company OMK 25 percent, and Japanese Sumitomo 10 percent, a press release from the company reads.

According to Newsru.com, the financial crisis have resulted in a 40 percent price reduction on the Nord Stream pipes.

Construction of the first line of the Nord Stream Pipeline is scheduled to commence on 1 April 2010; construction of line two is planned to start in spring 2011.

A tender on the first of the two Nord Stream parallel pipelines was conducted in 2007. That was won by Europipe and OMK.